Since our last post we've spent a fair amount of our time working at Aira Force, on a section of footpath above High Cascades.
Old path
The section of path that we've been working on had previously been repaired many years ago, but as the path was a bit "rough and ready" visitors were avoiding it which had caused the area next to the path to become eroded. This can be seen in the photograph above.
Path before commencing the rebuild
As the area is not very accessible, it was decided that some of the stone would be flown to site by helicopter. This was supplemented with useable stone from the original footpath and additional stone that we were able to gather from the surrounding area using our mechanical power barrow.
Completed lower section of path
To make the path blend in a little better, we adjusted the line to make it snake through the site rather than cut through in a straight line. The line was partially dictated by bedrock, which came to the surface at a couple of locations. To avoid having to chip away too much, we gave it a wide berth where possible.
Working in the snow
Our work was hampered on a couple of occasions by heavy snow which prevented us getting over to Ullswater or making it impossible to safely move large stones around. But on days with just a light scattering of snow we continued regardless.
Middle section after moving rock to site
After a few weeks of work we had pretty much completed the stone path. The new path is much more user-friendly and incorporates a couple of large stone drains to shed water away and prevent damage.
Middle section after completing the stone work
Unfortunately, due to the pressing job of gathering stone for our upland repairs, we weren't able to complete all the landscaping work in time. So we're hoping to get a bit of time later on in the year to tidy away some of the leftover rock and reseed the area and then the new path will be looking better than ever.
Completed top section of path