Monday 6 January 2020

Finishing off the footpath at Hole in the Wall

Our last upland work of the year, indeed the decade, was completing the section of footpath just below Hole in the Wall, on the way up to Striding Edge.


Joining up the path

We still had a sizeable section of path to complete and it was a race against the clock to get all the work finished before the onset of winter.
Newly landscaped section of path

Although there was a lot of rubble to dig through, most of the path was 'relatively' easy digging although we hit one section of solid bedrock towards the top of the path that slowed things down a bit. This all had to broken and prised out of the ground before the footpath could be built.

 Bedrock

You can see some of the bedrock that was taken out of the ground to the side of the path in both the previous and following photographs. When large quantities of rock are produced it often makes the landscaping difficult, especially in areas such as Hole in the Wall where there isn't a lot of surface rock visible.

Path before landscaping

To blend the area in with its surroundings, much of the rock had to be moved away from the path and buried. Then soil that had been excavated further up the path was carried downhill and used to cover over the rubble. Once this was done, as usual, the area was turfed and seeded.

Path after landscaping

You can see in the following photograph how the original path was widening as people wandered away from the original line (here covered by stone).
 Starting a new section

With the new path in place and the surrounding area landscaped with soil and turf, the footpath has been narrowed. Given time and plenty of grass seed, the areas around the path will become nicely vegetated. Any water running down the path will be shed away by the stone drain you can see in the photo below. All this combined will vastly reduce the amount of soil erosion.
Finished section of path

With the new path completed, the final job was to pitch up to an older section of path above where we were working. The path had originally been put in at ground level but over the years the soil has eroded away and had left a high step up on to the path. Eventually the path would have started to fall out, and people were already starting to avoid the step up (as seen to the left of the photo below). By adding this extra metre of path the original work will last much longer and the damage caused by people avoiding it will be prevented.

Pitching up to the old section

With the job completed and first few snowflakes of the year proving that winter was fast approaching it was time to head down off the fell and commence our winter work lower down in the valleys.