Building a stone footpath is slow work which is dependent on a wide range of variables such as; how hard the digging is, how busy the path is, the quality of rock, and the width of the path.
The following two photographs show roughly two months progress. In that time three of the team have worked on this section and roughly 30 metres of path have been pieced together.
Middle section, 21st June
Middle section, 16th August
Once a section of path is completed, it's time to landscape the path. The following two photos show the same bit of path before and after landscaping. The bank of spoil to the left has been levelled out, after removing any turf that would be covered over in the process, and this has been used to edge the path. Surplus stone has been dug into the ground around the path to give it a more natural look, and finally grass seed has been scattered over the whole area.
Middle section before landscaping
Middle section after landscaping
A section of landscaped path, further up from the previous photos can be seen below.
Freshly landscaped section of path
As we've moved higher up the path the digging has become more challenging. The path has become littered with large boulders and sections of bedrock which all has to be removed before the new stone footpath can be built. Occasionally a boulder may be too large to move, or the bedrock too hard to break and in those instances it can usually, with experience, be worked around.
Working in ground like this is obviously more challenging and tends to slow down progress, in addition more rock and less soil is excavated which creates more difficulties with landscaping.
Removing a sizeable chunk of bedrock from the path
We’ve now completed just over half of the path repairs up at Hole in the Wall so we’ll be working through until late autumn and returning to finish things off in spring next year.