The path that we're repairing had previously been worked on over 20 years ago. When this original path was built all the stone was collected by hand from the fell-side, this meant that the selection of rock was fairly limited. Because of this, smaller stone had to be used, the path had to be narrow and there was little landscaping carried out to help encourage people to stay on the path. All this has led to people wandering off the path and causing erosion problems. You can see in the photograph below that this has also produced an increased amount of rubble, which again leads to people not using the path.
Old pitching
It was therefore decided that extra stone would be flown to site by helicopter so that we could widen the path and improve upon the landscaping. As there is now a lack of suitable rock in the nearby area, without the use of a helicopter it's unlikely that we could have ever made these improvements. As part of our work extra drains are also being added to help shed water and to catch any surplus rubble.
Starting to replace the path
By using some of the original stone plus the stone that was flown in, after just a few weeks of work the path is now really taking shape. There's still a lot of of landscaping to do once the footpath is completed but we're progressing along nicely.
New section of path
Unseasonal snow
No comments:
Post a Comment