Bottom section before starting work on the path
The digging has, so far, been pretty good, we're not pulling too many large stones out of the ground and there's been no sign of any bedrock (which often has to be chipped out before we can lay the path). We've had both really hot and really wet weather over the last few weeks but only for a few days here and there, so nothing really out of the norm. We've also had one or two really busy days, but the worksite is easy to keep safe and there is plenty of room for people to get past. So, apart from a little extra time spent explaining about our work, it hasn't really affected things too much either.
After a few days work
As this path does get really busy at times (we're expecting lots more walkers during the summer holidays if we get some good weather) we're building the path a little wider than normal. Because of the extra width, we're maybe averaging a little under a metre a day at present.
The path starting to take shape
After just over a month, we're now reaching the point where we're starting to join sections of the path together before we leap-frog each other and start work again further up the path.
Almost ready to join two sections
With the sections joined, it's time to start filling in all the gaps with some of the soil that's been dug out. There's still plenty of landscaping work to do on this section but it's really starting to look like a footpath now.
After filling in the gaps
Volunteers at work in the rain